Peregrine Computer Consultants Corporation (PCCC) Data Center Power Outage Resolution

Apr 02, 2010
From approximately 1:18PM to 7:06PM, PCCC experienced a complete outage of our data center. The outage was the result of the Fire Department requiring that a complete shutdown of power. The culprit was an air conditioner compressor that seized, venting refrigerant and smoking rubber from the belt causing the fire suppression system to activate.